Tritech Engineering was appointed the mechanical contract for two single storey community nursing homes. The units were constructed off site using system build technology for the HSE with a combined floor area of 55,000 sq ft buildings to fulfil the HSE requirements for community nursing facilities and to combat the spread of infection providing modern high specification public health care facilities for elderly and high care dependency patients.

The mechanical engineering services comprises of LTHW systems serving LST radiator circuits, DHW & AHU circuits. Central AHU’s with DX cooling to day care and kitchen areas, exhaust systems, close control units to comms room, water & waste services, medical gas installations & BEMS system.

Scope of works

  • Mechanical services

Project Team

Client: HSE
Architect: PMCA
M/E Consultant: Axis Engineering
Main Contractor: Glenbeigh Construction
Project Duration: Ten Months
Value: €1,500,000