Published on in / Blog / by .

Tritech Engineering was appointed the mechanical services contract for the fit out of Kings Building, 152-155 Church Street, Dublin 7.  This project consisted of the fit-out of office space on ground, fourth fifth & sixth floors. The project was delivered in 2 phases with phase 1 fast-tracked delivering 80% of the contract in 12 weeks.

Scope of works

Mechanical Services Installation:

  • Fan Coil Units, new, relocation of existing & removals.
  • CHW & LTHW piped services.
  • Condensate pipework.
  • Close control units to comms room & tech rooms.
  • Water, Drainage & Ventilation Services to Ground Floor Showers & Micro Kitchens.
  • Heat recovery ventilation to all office floors.
  • Utility Tie Ins c/w Management of Application To Landlord For Consent.
  • BMS Controls.
  • Lead Co-ordinator for all specialist services.

Project Team

Architect: MCA

M/E Consultant: ARUP Consulting Engineers

Main Contractor: Structure Tone

Project Duration: Six Months

Value: €1,400,000