Tritech Engineering completed enabling works and provision of mechanical services for a 2000m2, four floor over basement extension for John Paul Construction. The project was delivered in 2015.

Scope of works
Mechanical Services Installation

  • Enabling Works including the relocation of AC units, gas services, radiators, ventilation plant, etc..
  • New incoming gas service to existing plantroom & new plantroom.
  • Rainwater Harvesting.
  • LPHW to all trench heating & radiators.
  • Fire smoke dampers and associated control panel retrofit to all existing ventilation.
  • Cylon BMS
  • Lead Co-ordinator for all specialist services.

Project Team
Architect: John Fleming Architects
M/E Consultant: Varming Consulting Engineers
Main Contractor: John Paul Construction
Project Duration: 6 Months
Value: €450,000

Project Team